Schedule & Calendar

  • Summer and Fall 2016: Conduits for utility relocation, drainage pipes and a retaining wall at the intersection of US 2 and VT 14 were installed.
  • January 2017 to May 2017: Relocate utilities – this work will be performed by telecommunications and electrical companies
  • Spring through Fall 2017: Advertise (March 15, 2017) and award construction contract, build access roads and install a temporary bridge, complete majority of reconstruction of US 2
  • 2018: New bridge is constructed
  • 2019: Install drainage northeast of VT14 bridge, restore landscaping disrupted by project